Construction began three months ago, with the first solar panels placed on the water in October.
The floating platforms, anchoring systems and cable connections have been specifically designed to withstand fluctuating water levels, wind and wave conditions.
The floating system, weighing approximately 8,000 tons, will feature solar panels resistant to high humidity and sunlight exposure.
Once operational, wind conditions, water levels and platform movements will be monitored remotely.
The project's Environmental Impact Assessment (EIA) report has been approved by Türkiye's Ministry of Environment, Urbanization and Climate Change.
Fish populations, water quality and other environmental indicators will be monitored throughout the installation and operational phases.